Mao Khe Thermal Power Plant Details
-
Location: Xuan Son, Binh Khe, and Trang An Wards, Dong Trieu Town, Quang Ninh Province.
-
Owner: Vietnam National Coal-Mineral Industries Group (TKV).
-
Total Investment: Over 10,400 billion VND (or 9,315 billion VND depending on the source).
-
Capacity: 440 MW (consisting of 2 units, 220 MW each).
-
Technology: Utilizes Circulating Fluidized Bed (CFB) boiler technology. This allows for the combustion of low-quality anthracite dust from the Dong Trieu – Uong Bi region and is more environmentally friendly than traditional pulverized coal technology.
-
Fuel: Anthracite dust type 6B.4.
-
Progress: Construction was completed on schedule; Unit 1 began operation in late 2012, with final plant acceptance in early 2013.
-
Role: Supplies electricity to the National Power Grid while increasing the resource value of TKV’s coal reserves.